The latest update from MNDOT is located here: 4-17 MNDOT Email
Wet weather slows start of construction
Greetings. Thank you for subscribing to our Hwy 57 construction project updates. We plan to send weekly updates to help you anticipate what's planned to help you travel through town and also assist any visitors or customers who are coming to Mantorville.You will note a phrase we often use "weather permitting." That notes how weather can dictate progress and is something we don't control.
Crews have been limited because of the weather, but it's possible work will be taking place during the latter part of the week with crews milling up pavement and stockpiling it. So stay alert to the signs, equipment and crew members to ensure this is a safe project.
It's uncertain, but watch for crews who may be able to replace one water main crossing at 7th or 9th toward the end of the week but that is yet to be determined.
Weekly meetings
Our contractor, Elcor Construction will be meeting in-person weekly with community members.
Elcor will be at the County Seat Coffee House, 1 5th St W, Mantorville, MN 55955, at 2 p.m. each Wednesday, beginning April 24.
You are invited to come and ask questions about the project.
No comments:
Post a Comment