The last few weeks have seen many setbacks and challenges with our on-going street projects. I wanted to share the latest communication we have had from the crew working on third street.
Subject: Mantorville, MN - 2019 Street & Utility Improvements project - week
of July 29th
Good Evening,
This email will serve as a notification of the work to expect within the
week for the 2019 Street & Utility Improvements project which encompasses
work within Walnut Street, 3rd Street, Clay Street and the intersections of
Clay St & 4th St and Walnut St & 4th St.
Construction items completed last week:
* All the underground utility lines have been constructed and are in
operation.
* The roadways have been constructed to aggregate base.
* Concrete curb & gutter has been constructed within the project and
concrete sidewalk work has begun.
Below are a list of Construction items scheduled to take place this week:
* Driveway and sidewalk construction will be taking place over the next
few days. Please do not drive on newly placed concrete for 7 days.
* Middle of this week, Elcor Construction will begin shaping the gravel
roadway in preparation for paving.
Please park on side roads and within the alleyway over the next week to
allow concrete driveway and roadway construction to take place.
* Paving is scheduled for the first part of next week.
* Ditch grading and restoration work to follow over the next few weeks.
This schedule is weather dependent and is subject to change.
*Reminder: Please mark garbage cans with your address and set them out near
the road the night prior to your scheduled garbage day. Elcor will bring
them to a central location to be collected and bring them back at the end of
the day.
If you have any questions or concerns feel free to contact me at any time.